Ratify agreement with HDR Engineering Inc., combined water and sewer infrastructure needs assessment BEFORE THE BOARD OF COUNTY COMMISSIONERS
LEWIS COUNTY, WASHINGTON
IN THE MATTER OF: RESOLUTION NO. 21-450
RATIFY AN AGREEMENT WITH HDR ENGINEERING
INC. FOR PREPARATION OF A COMBINED WATER
AND SEWER INFRASTRUCTURE NEEDS
ASSESSMENT
WHEREAS, Lewis County received Coronavirus State and Local Fiscal Recovery
Funds from the Department of Treasury to be allocated water and sewer
infrastructure improvement projects; and
WHEREAS, the Public Works Director executed a Professional Services Agreement
with HDR Engineering Inc. on October 20, 2021, to provide professional services
to identify and prioritize water and sewer infrastructure needs for Lewis County;
and
WHEREAS, pursuant to Resolution 21-038, ratification by the Board of County
Commissioners (BOCC) is required for all contracts, projects, agreement, grant
applications, contract amendments and change orders involving expenditures
totaling between $50,000 and $200,000.
NOW THEREFORE BE IT RESOLVED that a consultant agreement previously
executed by Public Works is hereby ratified by the Board of County
Commissioners.
DONE IN OPEN SESSION this 21st day of December, 2021.
Page 1 of 2 Res. 21-450
APPROVED AS TO FORM: BOARD OF COUNTY COMMISSIONERS
Jonathan Meyer, Prosecuting Attorney LEWIS COUNTY, WASHINGTON
Amber Smith Lindsey R. Pollock, DVM
By: Amber Smith, Lindsey R. Pollock, DVM, Chair
Deputy Prosecuting Attorney
ATTEST: •'�°""g--D kgsF• Sean D. Swope
•�'� OF . I•
5®an D. Swope, Vice Chair
0•
•J cn„+
•
1V ,$q.5•
Rieva Lester '•sy - ,se`,: F. Lee Grose
Rieva Lester, F. Lee Grose, Commissioner
Clerk of the Lewis County Board of
County Commissioners
Page 2 of 2 Res. 21-450
PROFESSIONAL SERVICES AGREEMENT
BETWEEN LEWIS COUNTY AND HDR ENGINEERING INC.
PARTIES TO THE CONTRACT
This Contract is made and entered into by and between Lewis County hereinafter referred to collectively
as the "COUNTY" and HDR Engineering Incorporated, hereinafter referred to as the "CONSULTANT."The
COUNTY and the CONSULTANT together,are hereinafter referred to as the "PARTIES."
Lewis County
351 NW North St
Chehalis WA 98532
HDR Engineering, Inc.
600 University St. Ste. 500,
Seattle, WA 98101
206-826-4737
PURPOSE
The COUNTY hereby enters into a contract agreement with HDR Engineering, Inc.to provide engineering
and architectural services for the preparation of a comprehensive water and sewer infrastructure needs
assessment that includes:
• Identifying public utility water and sewer infrastructure projects within all incorporated and
unincorporated areas of the COUNTY including: the cities of Centralia, Chehalis, Napavine, PeEll,
Winlock,Vader,Toledo,Onalaska,Mossyrock,Morton,and Randle;unincorporated communities;
the Ports of Centralia and Chehalis;and the water and sewer special purpose districts within Lewis
County.
• Comprehensive infrastructure needs assessment report
Further details of the services provided can be found in Exhibit A, Scope of Work, attached to this
agreement.
PERIOD OF PERFORMANCE
The term of this Agreement shall commence on the 18 day of October , 2021 and shall, unless
terminated or renewed as provided elsewhere in this Agreement, terminate April 1, 2022, but may be
extended by mutual agreement.
STATEMENT OF WORK
The CONSULTANT agrees to provide to the COUNTY services and any material set forth in the project
narrative identified as Exhibit"A" during the Contract period. CONSULTANT provides such services as an
independent contractor using CONSULTANT'S own officers, agents, employees, or contractors. This
Contract shall not be construed to make the COUNTY an employer or joint employer of CONSULTANT or
any of CONSULTANT's officers, agents, employees, or contractors. The standard of care for
CONSULTANT's services shall be the care and skill ordinarily used by members of CONSULTANT's
profession practicing under the same or similar circumstances at the same time and in the same locality.
ESTIMATES
Any estimates of project cost, value or savings provided by CONSULTANT are intended to allow a
comparative evaluation between alternatives and do not constitute a detailed evaluation or prediction of
actual project costs,value or savings. Any such estimates are made on the basis of information available
to CONSULTANT and on the basis of CONSULTANT's experience and qualifications, and represents its
judgment as an experienced and qualified professional engineer. However, since CONSULTANT has no
control over the impact of various factors that impact the actual project cost, value or savings,
CONSULTANT does not guarantee that the actual project cost, value or savings will not vary from
CONSULTANT's estimates.
FUNDING/COMPENSATION
Funding for this Contract is provided by Department of Treasury,through the American Rescue Plan Act.
Total CONSULTANT compensation will be based on invoiced amount and will not exceed $67,900 unless
this Contract is subsequently amended by both parties.
BILLING PROCEDURES AND PAYMENT
The CONSULTANT shall provide the COUNTY with monthly invoices due 30 days after receipt describing
and documenting to the COUNTY'S satisfaction the work performed. The CONSULTANT must provide a
breakdown of expenses, identifying what was expended and when. Any fees for additional services will
be discussed and approved by the COUNTY in advance of services being performed.
The COUNTY may, in its sole discretion, terminate the Contract or withhold payments claimed by the
CONSULTANT for services rendered if the CONSULTANT fails to satisfactorily comply with any term or
condition of this Contract and fails to cure such failure within a period of 10 days following written notice
of thereof.
MODIFICATIONS
Either party may request changes in this Agreement. Any and all modifications agreed to by the parties
shall be memorialized in a writing signed by each of the parties.
TERMINATION FOR DEFAULT
If the CONSULTANT defaults by failing to perform any of the obligations of this Agreement or becomes
insolvent or is declared bankrupt or commits any act of bankruptcy or insolvency or makes an assignment
for the benefit of creditors,the COUNTY may,by depositing written notice to the CONSULTANT in the U.S.
mail, postage prepaid,terminate the Agreement,and at the COUNTY's option,obtain performance of the
work elsewhere. However, the COUNTY will not terminate for default without providing CONSULTANT
written notice of the default and a period of 10 days to cure. If the Agreement is terminated for default,
the CONSULTANT shall not be entitled to receive any further payments under the Agreement until work
called for has been fully performed. Any extra cost or damage to the COUNTY resulting from such
default(s)shall be deducted from any money due or coming due to the CONSULTANT. The CONSULTANT
shall bear any extra expenses incurred by the COUNTY in completing the work, including all increased
costs for completing the work, and all damage sustained, or which may be sustained by the COUNTY by
reason of such default.
If a notice of termination for default has been issued and it is later determined for any reason that the
CONSULTANT was not in default,the rights and obligations of the parties shall be the same as if the notice
of termination had been issued pursuant to the Termination for Public Convenience paragraph hereof.
TERMINATION FOR PUBLIC CONVENIENCE
The COUNTY may terminate the Agreement in whole or in part whenever the COUNTY determines, in its
sole discretion that such termination is in the interests of the COUNTY. Whenever the Agreement is
terminated in accordance with this paragraph, the CONSULTANT shall be entitled to payment for actual
work delivered at unit contract prices for completed items of work. An equitable adjustment in the
Agreement price for partially completed items of work will be made,but such adjustment shall not include
provision for loss of anticipated profit on deleted or non-completed work. Termination of this Agreement
by the COUNTY at any time during the term, whether for default or convenience, shall not constitute a
breach of contract by the COUNTY.
WITHHOLDING PAYMENT
In the event the CONSULTANT has failed to perform any substantial obligation required under this
Contract the COUNTY shall notify the CONSULTANT in writing. If that failure has not been cured within
thirty days after notification, then the COUNTY may, upon written notice, withhold all monies due and
payable to CONSULTANT,without penalty, until such failure to perform is cured or otherwise adjudicated.
OWNERSHIP OF ITEMS PRODUCED
All writings, programs,data, public records or other materials prepared by the CONSULTANT and/or their
subcontractors, in connection with the performance of this Agreement shall be the sole and absolute
property of the COUNTY. Any modification or reuse of such items for purposes other than those intended
by this Agreement shall be at COUNTY's sole risk and without liability to CONSULTANT.
CONTRACT MANAGEMENT
The Contract Manager for each of the PARTIES shall be the contact person for all communications and
billings regarding the performance of this Contract.
The COUNTY representative shall be Josh Metcalf,2025 NE Kresky Ave,Chehalis,WA 98532; 360-
740-2762,josh.metcalf@lewiscountywa.gov
The CONSULTANT representative shall be Jeff Hansen,905 Plum Street SE,Ste 200, Olympia,WA
98501,jeff.hansen@hdrinc.com
INDUSTRIAL INSURANCE
With respect to the performance of this Contract,CONSULTANT shall comply with Title 51 of the Revised
Code of Washington, the Industrial Insurance Act, for injuries to its employees and agrees that COUNTY
shall have no obligations under that Title to any of CONSULTANT's officers, agents, employees, or
contractors.
INDEMNITY
CONSULTANT agrees to indemnify,defend and hold COUNTY and COUNTY'S officials, employees, agents,
volunteers, and insurers harmless from and against any and all claims, damages, losses and expenses,
including but not limited to court costs, attorney's fees and alternative dispute resolution costs, for any
personal injury, for any bodily injury, sickness, disease or death and for any damage to or destruction of
any property (including the loss of use resulting therefrom) to the extent caused by any negligent or
wrongful act or omission of CONSULTANT or CONSULTANT's officers,agents,employees,or contractors.
CONSULTANT's indemnification obligation shall not be limited in any way by the Washington State
Industrial Insurance Act, RCW Title 51, or by application of any other workmen's compensation act,
disability benefit act or other employee benefit act, and CONSULTANT hereby expressly waives any
immunity afforded by such acts. The foregoing indemnification obligations were mutually negotiated by
the parties as a material inducement to enter into this Contract.
COUNTY reserves the right, but not the obligation, to participate in the defense of any claim, damages,
losses or expenses and such participation shall not constitute a waiver of CONSULTANT's indemnity
obligations herein.
The indemnity obligations herein shall survive this Contract's completion,expiration or termination.
SEVERABILITY
If any term or condition of this Agreement or the application thereof to any person(s)or circumstances is
held invalid, such invalidity shall not affect other terms, conditions or applications, which can be given
effect without the invalid term, condition or application. To this end, the terms and conditions of this
Agreement are declared severable.
ORDER OF PRECEDENCE
This Contract is entered into,pursuant to,and under the authority granted by applicable federal and state
laws. The provisions of the Contract shall be construed to conform to those laws. In the event of an
inconsistency in the terms of this Contract,or between its terms and any applicable statute,rule,or policy
or procedure,the inconsistency shall be resolved by giving precedence in the following order:
• Applicable federal laws and regulations,
• State law,
• Washington Administrative Code,
• This Contract, and
• Any other provision, term or material incorporated herein by reference or otherwise
incorporated.
This Contract represents all the terms and conditions agreed upon by the PARTIES. No other statements
or representations,written or oral, shall be deemed a part hereof.
CONFORMANCE AND CHOICE OF LAW
If any provision of this Contract violates any statute or rule of law of the State of Washington, it is
considered modified to conform to that statute or rule of law. This Contract shall be construed under the
laws of the State of Washington, except with respect to any choice of law rules. Venue for any action
arising out of this Contract or its performance shall be in the Superior Court of Washington in and for
Lewis County or in the U.S. District Court for the Western District of Washington,Tacoma Division.
APPROVAL
This Contract shall be subject to the written approval of the COUNTY authorized representative and shall
not be binding until so approved. The Contract may be altered, amended, or waived only by a written
amendment executed by both PARTIES.
This CONTRACT is executed by the persons signing below who warrant that they have the authority to
execute the Contract.
LEWIS COUNTY CONSULTANT
Josh Metcalf Name Rob Berman
Director, Public Works Title Sr.Vice President
10/18/2021 10/20/2021
DATE DATE
2020-10-04
"EXHIBIT A"
Lewis County
Comprehensive Water and Sewer Infrastructure Needs Assessment
Scope of Services
Background
Lewis County is acting as the lead agency for an assessment which will include identifying
public utility water and sewer infrastructure projects within all incorporated and unincorporated
areas of the County including: the cities of Centralia, Chehalis, Napavine, PeEll, Winlock, Vader,
Toledo, Onalaska, Mossyrock, Morton, and Randle; unincorporated communities; the Ports of
Centralia and Chehalis; and the water and sewer special purpose districts within Lewis County.
This project will identify the water and sewer needs, issues, and challenges for each public
water and/or sewer utility and prepare a coordinated needs assessment of infrastructure
expansion and improvements throughout Lewis County.
The purpose of this assessment is to provide information that will support the decision-making
process of the Lewis County Board of County Commissioners (BOCC) in allocating funding
received from the US Department of the Treasury through the American Rescue Plan Act. HDR
Engineering, Inc. (HDR)will provide support to the County in conducting this assessment,
according to the scope of services outlined below.
Project meetings will either be held in a virtual setting using WebEx, Microsoft Teams or other
similar method, or conducted in person. For project meetings that are conducted in person, the
current HDR and County protocols regarding personal interactions during the COVID-19
pandemic will be followed by all HDR personnel in attendance.
Task 1 Project Management
Objective
The purpose of this task is to monitor, manage and adjust scope, schedule, and budget as well
as provide monthly status reporting, accounting, and invoicing.
HDR Services
1. Coordinate and manage the project team.
2. Prepare monthly status reports describing the following:
a. Services completed during the month.
b. Services planned for the next month.
1
2020-10-04
c. Needs for additional information.
d. Scope/schedule/budget issues.
e. Schedule update and financial status summary.
3. Prepare monthly invoices formatted in accordance with Contract terms.
4. HDR Project Manager will schedule monthly project management coordination calls with the
County Project Manager to review project scope, schedule, and budget issues.
County Responsibilities
1. Participate in monthly project management coordination calls.
2. Timely processing and payment of invoices.
3. Review and process contract change requests and amendments, if needed.
Assumptions
1. The project will be completed within four (4) months after receiving Notice to Proceed. The
anticipated project initiation is mid-October 2021, and the expected completion date is
February 28, 2022.
2. One (1) project management coordination call will be held per month with one (1) hour of
HDR project manager time required for each including preparation, attendance, and notes.
3. HDR will perform internal QC review of deliverables identified in this Scope of Services
before they are submitted to County. The HDR QC reviewer, not involved directly in the
project, will provide a review of deliverable products. The Project Manager will coordinate
with the reviewer to implement the QC review process.
Deliverables
1. Scope of services (PDF format).
2. Monthly status reports and invoices, including project schedule and budget updates
(emailed in PDF format).
3. Project management coordination call summary notes (email).
Task 2 Data Gathering
Objective
The objective of this task is to formally initiate the project with County, request background
information, conduct information gathering interviews, and review available information related
to the coordinated needs assessment. This information will inform understanding of existing
capital improvement programs (CIPs), water and sewer needs, and other data needed for the
assessment.
HDR Services
1. Meet with County staff and others identified by the County Project Manager(e.g., Public
Works Director, Economic Development Council [EDC] infrastructure lead, and
finance/budget staff) to kick-off the project, discuss priorities and available information to be
reviewed, and identify other key stakeholders and their potential issues and concerns.
2
2020-10-04
2. Develop kick-off meeting summary notes, including a log of decisions made during this
meeting. This decision log is to be updated as needed throughout the project.
3. Develop Inventory Questionnaire (Draft and Final)for Lewis County and all public
water/sewer utilities to complete.
4. Identify and request available materials for review, including, but not limited to the following:
a. CIP table(s), capturing at least a 10-year planning horizon, providing project
description, costs, and justification/need and brief narrative summary of any key
assumptions in developing cost estimates (e.g., unit costs for piping, and
contingency assumptions).
b. GIS data available for the CIP and/or proposed projects.
5. Review incoming data provided by questionnaire respondents and request clarification when
necessary.
6. Maintain and update a data tracking spreadsheet and review progress of data transfer with
County representatives.
7. Schedule and facilitate interview meetings with participating entities, seeking additional
insights into water and sewer infrastructure needs and documenting findings.
8. Prepare compiled list of water/sewer projects (i.e., the unprioritized infrastructure needs
inventory).
County (and other entities) Responsibilities
1. Provide review comments on Draft Questionnaire, within one (1)week of submittal.
2. Provide requested water and sewer CIP data and documents, according to a schedule
mutually defined by HDR and the County.
3. Assist with identifying public water/sewer utility point of contacts and coordination to
complete interview meetings.
4. Participate in interview meetings.
5. Provide review comments on Draft Unprioritized Infrastructure Needs Inventory, within one
(1)week of submittal.
Assumptions
1. HDR has a reasonable right to rely on information provided to HDR from the County and
the public water/sewer utilities for the use and preparation of this assessment and/or
deliverables in this scope of services.
2. An infrastructure needs inventory will be developed based on available submitted current
and proposed projects from Lewis County and its' entities.
3. The public entities to be contacted regarding project lists and information are anticipated to
be:
a. City of Centralia
b. City of Chehalis
c. City of Morton
d. City of Mossyrock
3
2020-10-04
e. City of Napavine
f. City of Toledo
g. City of Vader
h. City of Winlock
i. Town of Pe Ell
j. Lewis County (i.e., County systems serving other Unincorporated Communities)
k. Ports of Centralia and Chehalis
I. Lewis County Water and Sewer Districts (6 districts)
4. Interview meetings are planned to occur as in-person meetings, unless COVID-19
protocols/requirements in place at the time of the meetings dictate otherwise and/or if some
meeting participants request that the meetings be held virtually. Interview meetings are
assumed to be 45 minutes in length, with two HDR staff participating in each. The meetings
will be scheduled over the course of four days. The budget includes travel time and
mileage expenses covering two HDR staff traveling for the meetings.
5. If COVID-19 protocols change during the course of the project that necessitate interview
meeting be held virtually, and/or if some meeting participants request that meetings be held
virtually, WebEx will be used as the platform to facilitate remote interview meetings.
6. All other communications will be via email and phone.
7. All documents will be provided in electronic (Word, Excel, and/or PDF)formats.
8. No project-specific site visits are included.
Deliverables
1. Kickoff meeting summary notes, and initial decision log (PDF format).
2. Data request tracking spreadsheet (updated as materials are provided by the County and
its' entities).
3. Inventory Questionnaire (draft and final, Word format).
4. Unprioritized infrastructure needs inventory (draft and final, Excel format).
Task 3 Analyze Data and Develop Prioritized Inventory
Objective
The objective of this task is to evaluate current and proposed water and sewer infrastructure
projects and develop a prioritized inventory to identify maximum benefits of investment across
Lewis County.
HDR Services
1. To place all project costs on a common footing and account for recent increases in labor
and material costs, HDR will escalate previously developed cost estimates to 2021 dollars
through use of the Engineering News-Record Construction Cost Index, evaluate differences
in unit cost and contingency assumptions, and make adjustments based on professional
judgement to yield costs that can more readily compared.
4
2020-10-04
2. Develop rating criteria incorporating metrics that represent factors such as: critical need,
schedule, safety, regulatory requirements, resilience, cost, equity, funding eligibility, and
other aspects deemed relevant to Lewis County and its' entities with a focus on multi-
beneficial investments.
3. Qualitatively assess social, environmental, and financial benefits and impacts of submitted
projects by preparing preliminary project ratings (i.e., scorings) using the developed rating
criteria. Provide preliminary ratings to County for review ahead of review meeting.
4. Facilitate a project rating review meeting, up to two (2) hours long, to discuss rating criteria,
weighting, preliminary project scoring, possible project bundling, and rating refinement.
5. Following the meeting, prepare a prioritized inventory of water and sewer project needs
based on final project ratings. This will be documented in the Task 4 deliverable.
County Responsibilities
1. Review rating criteria framework and provide consolidated comments within one (1)week of
draft submittal.
2. Review preliminary project ratings prior to inventory review meeting.
3. Participation in the inventory review meeting.
4. Interface with EDC infrastructure lead on other needs assessments (e.g., transportation)
and rating criteria used throughout the County.
Assumptions
1. No project cost estimating will be performed by HDR; only adjustments to previously-
prepared cost estimates will be made to support comparisons between projects.
2. Projects scheduled to obligate funds by December 31, 2024, and expend costs by
December 31, 2026 will be prioritized.
3. All other projects submitted that are firmly scheduled beyond the obligate-by and expend-by
dates, will be tabulated for future information purposes only, not included in this needs
assessment prioritization.
4. The project rating review meeting will be in-person at County offices. The budget includes
travel time and mileage expenses covering two HDR staff traveling for the meeting.
Deliverables
1. Rating criteria framework and weighting (draft and final; Word or Excel format).
2. Preliminary project ratings (draft; Excel format).
3. Inventory review meeting summary (PDF format).
4. Prioritized inventory (Excel format). This will not be submitted for review as part of this task;
rather, it will be incorporated into the Task 4 deliverable.
5
2020-10-04
Task 4 Prepare Comprehensive Needs Assessment Report
Objective
The objective of this task is to compile an infrastructure needs assessment report that will
provide input for use by County decision-makers in allocating funding.
HDR Services
1. Prepare coordinated infrastructure needs assessment report (draft and final), covering water
and sewer improvements.
2. Participate in up to two (2) meetings with the County to discuss the prioritized inventory and
needs assessment report.
County Responsibilities
1. Review the comprehensive needs assessment report and provide timely, consolidated
comments.
2. Present comprehensive inventory to BOCC to discuss prioritization and solicit feedback on
recommended infrastructure improvements.
3. Prepare mapping required to supplement comprehensive infrastructure needs inventory
(e.g., GIS-based mapping that depicts locations of proposed CIP projects).
Assumptions
1. Development of the comprehensive needs assessment is envisioned to be an iterative
process, wherein draft materials are developed and presented to County staff and the
BOCC, with refinements made based on input from County staff, the BOCC and other
stakeholders.
2. The needs assessment report (draft and final) is expected to be no more than 20 pages in
length.
3. The County or EDC will conduct GIS mapping of CIP projects.
4. The comprehensive needs assessment report will provide input to the County decision-
making process regarding project funding allocation. The report itself will not document
allocation decisions, which will be made by the County and other stakeholders.
5. Meetings will be in-person at County offices. The budget includes travel time and mileage
expenses covering two HDR staff traveling for the meetings.
Deliverables
1. Comprehensive infrastructure needs assessment report (draft and final; PDF format).
6
2020-10-04
Schedule
This project will be completed within four(4) months of notice to proceed. Anticipated schedule
milestones are outlined in the table below,
Task/ Milestone Target Completion
Kickoff October 18, 2021
Data Gathering (incl. interview meetings) Oct—Nov 2021
Analyze Data and Develop Prioritized Inventory Nov—Dec 2021
Comprehensive Needs Assessment Report Dec 2021 —Feb 2022
Fee
The fee breakdown associated with the above tasks is summarized below.
Task Fee
Task 1 - Project Management $ 5,300
Task 2 - Data Gathering $ 29,100
Task 3 -Analyze Data and Develop Prioritized Inventory $ 17,200
Task 4 - Comprehensive Needs Assessment Report $ 16,300
Total $ 67,900
*Escalation(3.5%)is included,to account for an assumed amount(20%)of the work occurring in 2022.
7
BOCC AGENDA ITEM SUMMARY
Resolution: BOCC Meeting Date: Dec. 21, 2021
Suggested Wording for Agenda Item: Agenda Type: Deliberation
Ratify an agreement with HDR Engineering Inc. for preparation of a combined water and sewer
infrastructure needs assessment
Contact: Josh Metcalf Phone:
Department: PW - Public Works
Description:
This resolution will ratify a consultant agreement and supplements over $50,000 for the
Professional Services contract with HDR Engineering Inc. for preparation of a combined water and
sewer infrastructure needs assessment for Lewis County
Approvals: Publication Requirements:
Publications:
User Status
Becky Butler Pending
PA's Office Pending
Additional Copies: Cover Letter To:
Becky Butler